Texas Construction Law Updates

Nick Brooks -

Wednesday, May 31, 2017

Under the Texas Civil Practice & Remedies Code, “a contract stipulation that requires a claimant to give notice of a claim for damages as a condition precedent to the right to sue on the contract is not valid unless the stipulation is reasonable. A stipulation that requires notification within less than 90 days is void.” […]

...read more